Tip #36 – Avoid New Product Procrastination

Pipeline Accelerator Tip #36: Avoid Organizational Procrastination

Critical Chain Project Planning strips the safety from each individual task.

All we plan for is touch time. How long it should take if everything goes perfectly and you aren’t interrupted.

That sounds like it would guarantee that the smallest hiccup could cause the project to finish late.

That’s why CCPM puts half of the safety back as a shared buffer at the end of the project.

That eliminates procrastination behaviors like student syndrome, apple polishing, and sandbagging.

See for yourself with this short video

 