Misaligned priorities are one of the biggest killers of innovation momentum. If your team is juggling too many projects with unclear priorities, workflows get muddled, and timelines slip. This post, adapted from my original IndustryWeek series, explores how setting crystal-clear new product priorities helps teams move faster, stay focused, and deliver more.

In the previous articles in this series you learned how to plan robust projects and manage pipeline entry to avoid derailing work already underway. Now that your project has entered execution, you want it to flow like a relay race—easily and swiftly with a minimum of interruptions.

Shared Resources are a Reality

Even if your business is large enough to have dedicated teams for each project, there will be some resources that must be shared across multiple projects—resources with a particular expertise that is only used sparingly throughout a project or capital-intensive resources like testing labs or pilot plants.

And that means everyone must know what the priorities are to avoid having a project become unnecessarily hung up waiting for resources. That’s impossible without clear, stable priorities. That means your people need to know the answer to these two questions—and hopefully without a lot of effort.

  1. What should I be working on now?
  2. What should I work on next?

These may sound like simple questions, but in most companies, the answer is resolved by the “Wheel Method”— the squeaky wheel or the big wheel. Whoever makes the most noise or has the most influence, gets the resources.

The conventional wisdom that causes much of this is that strategic priorities should drive all priorities—including day to day execution. In fact, some project managers learn to manipulate this to their project’s advantage—not necessarily what is best for the company.

Don’t get me wrong. Strategic priorities are critical, most importantly as part of governance, where they help you to decide which opportunity should be the next to start. It’s just that they are very difficult to interpret at the execution level.

The good news is that there is another, more effective approach. Bear with me through this next example and any remaining fog should lift.

Project Greenlight is your company’s newest program and your highest strategic priority. At the 3-month point, Greenlight is 25% complete and looking like it will finish well ahead of the promised launch date.

At the same time, Project Yellowlight, your second highest priority, is looking like it will just barely finish on time one month from now.

That’s when you hit a speed bump—both projects need the same shared testing resource to complete the next three weeks of work. Following strategic priorities, Project Greenlight gets the resource first. Consequently, Project Yellowlight finishes three weeks late and misses the promised due date for an important customer.

So what’s the alternative? If instead the risk of finishing late is used to prioritize the resources, Project Yellowlight gets priority and finishes just on time while Greenlight still has plenty of buffer left to assure an on-time finish—a much better outcome all the way around.

Again, following the model of a relay race, once a project has started running, strategic priorities become secondary and the project that is most at risk of finishing late must get priority access to resources–especially if the goal is an on-time finish.

The Buffer that Synchronizes

In critical chain project management, you plan every task as if everything will go perfectly. But since you know that something will go wrong, you add a project buffer at the end. That buffer is equal to 50% of the length of the critical chain of the project. It turns out that the buffer also becomes an important tool for synchronizing priorities.

If you plot the buffer status of all your projects on the same chart, you will get a clear visualization of which project should get the resource. The vertical axis is the percentage of buffer burned. The horizontal is the percentage of the critical chain completed. Projects that are burning buffer faster than they are completing critical chain tasks will be quite obvious—residing above a diagonal from the lower left to the upper right.